This project will complete interior construction of 11,000 sq/ft of shell space. Included work is on the first and third floors of the addition completed in 2012, known as phase 2. First floor includes finish out of four laboratories, seven offices and other support areas and restrooms. Third floor includes finish out of three laboratories with associated support spaces, nine offices and one restroom. The projects may also include renovation of two existing labs within Castetter Hall.
Tasks
• HVAC
• Plumbing/Piping
• Duct Detailing
• Pipe Detailing
• BIM Detailing/Coordination
• Duct Fabrication
• Pipe Pre-Fabrication
• Training/Start-up

Features
• 11,000 Sq/Ft
• Education/Laboratory Remodel