This project was a mechanical system renovation at the hospital’s central plant to accommodate the addition of an 11-story structure. The facility was staffed 24 hours a day and had to remain functional throughout the renovation process as it served as the energy center for the entire hospital campus. An oil chiller, radiators, cooling tower, and cogeneration system were added to the facility; all work, including system outages, had to be carefully coordinated with the hospital staff so they did not disrupt patient care.
Features:
Tasks:
- Plumbing/piping
- Pipe Fabrication
- Welding
- Detailing
- Commissioning assistance
Features:
- Plan & spec bid
- 18,575 sq/ft
- Cogeneration system addition
- Oil Chiller
- Cooling towers